Program Guidance for the 2008 New Jersey Environmental Quality Incentives
Program (EQIP)
Agricultural producers and eligible land owners or land managers may apply
for conservation practices that:
- are included in an approved Conservation Plan; and
- will achieve a positive environmental benefit; and
- are listed in this 2008 Program Guidance.
If an application is approved based on available funding, NRCS will
develop a draft contract listing the payments to be made upon successful
practice completion. Applicants will have ample opportunity to review
the proposed payments prior to contract signature. No practices can be
installed until the final contract is approved by NRCS, unless a waiver
is granted by the State Conservationist.
Although based on the average cost to implement typical conservation
practices in NJ, practice payments are made regardless of actual cost to
the contract holder.
Each installed practice must meet the minimum design requirements in
the applicable NRCS Conservation Practice Standard in order to receive
the contract payment.
The payment will be based on the extent (amount) of the conservation
practice actually performed, not the cost.
To apply, applicants must complete a program application and the
Conservation Planning Worksheet available
below. Applicants
must also meet all applicable Highly Erodible Land and Adjusted Gross
Income provisions, and establish or update all farm and persons records
before NRCS will process their application. Details can be found in the
Applying for Federal Farm Conservation Programs available
below.
Beginning Farmers and
Limited Resource Producers installing
structural practices are eligible for a higher payment contribution by
NRCS toward the completion of the practices. These applicants may be
subject to a review of their qualifying documents prior to contract
approval.
Current payment rates are found in the Schedule of Program Payments
on the NJ Conservation Programs web page.
Information about conservation practices can be found in the electronic
Field Office Technical Guide or on practice
job sheets available through your local NRCS office/USDA Service Center.
The following documents require
Adobe Acrobat.
EQIP
2008 Program Guidance (61 kb)
updated October 23,
2007
Applying
for Federal Farm Conservation Programs (54 kb)
Conservation
Planning Worksheet (35 kb)
What
Is a Conservation Plan? (162 kb)
Eligible applications will be grouped into “funding pools”, with the
highest ranked applications in each pool selected for contract
development. There will be five funding pools for 2008: Cropland (no
livestock); Beef & Dairy operations; Other Livestock operations;
Aquaculture operations; and Beginning Farmers (BF) and Limited Resource
Producers (LRP). A minimum of 10% of available funds will be provided to
the BF & LRP pool.
In addition to meeting the quality standards in each Conservation
Practice Technical Standard, the following guidelines are used to
determine whether practices are eligible for program payments. Practices
are listed by the resource area. Conservation practices eligible for payment assistance under the NJ
program in 2008 are listed alphabetically under the
following resource areas:
Program payments are
made according to the practice schedule in the Conservation Contract and
are based on the extent of the practice performed. For practices marked
“MGT”, three consecutive years of the practice will be scheduled in
consultation with the contract holder, as long as the contract meets all
other policy requirements.
Program payments for these management practices (marked “MGT”) will
be made for each year the practice meets NRCS standards. If the practice
does not meet standards, no payment will be made; and the payment will
not be re-scheduled unless the contract holder provides a written
justification to the State Conservationist for approval. If two or more
years of the practice are forfeited due to non-compliance, the contract
will be in violation and liquidated damages may be sought.
Additionally, for Irrigation Water Management and Prescribed Grazing:
The first year of the MGT
payment will be scheduled for the year after all on-the-ground
components required to carry out the practice are scheduled to be
installed. This includes all irrigation appurtenances and all fencing
and watering systems for grazing operations.
All active cropland is
eligible.
Air Resources Management (MGT)
Use alternative fuels - E85 or bio-diesel (B20 or higher) - for on-farm
agricultural activities.
Agrichemical Handling Facility
Install a permanent structure with an impervious surface to provide an
environmentally safe area for the mixing and handling of pesticides and
fertilizers used on agricultural lands.
Conservation Cover
Establish new permanent vegetative cover on cropland to protect soil and water
resources.
Conservation Crop Rotation (MGT)
Establish a new crop rotation system, including the introduction of higher
residue crops in rotation with at least two other crops, in order to reduce or
control sheet and rill erosion to the soil “T” level.
Contour Buffer Strips
Establish narrow strips of permanent, herbaceous vegetation across the slope and
alternate with wider cropped strips to reduce sheet and rill erosion, reduce
transport of sediment and other contaminants, or to enhance wildlife habitat.
Payment is made on the buffer strip portion of the field only.
Cover Crop (MGT)
Annually establish grasses or legumes for seasonal cover to reduce sheet and
rill erosion sequester carbon in plant biomass and soils, increase soil organic
matter, capture and recycle excess nutrients, promote biological nitrogen
fixation, or reduce particulate emissions into the atmosphere.
Critical Area Planting
In critical areas disturbed by the installation of erosion control measures,
plant perennial vegetation such as trees, shrubs, grasses, or legumes.
Diversion
Construct a channel across the slope with a supporting ridge on the lower side
to interrupt water flow on slopes, reduce runoff damage, or divert water away
from active gullies or critically eroding areas.
Field Border
Establish a strip of permanent vegetation at the edge or around the perimeter of
a field to reduce erosion from wind and water or manage insect populations.
Filter Strip
Establish herbaceous vegetation in a strip between cropland and sensitive areas
to reduce sediment, organics and dissolved contaminant loadings in runoff, or
serve as Zone 3 of a Riparian Forest Buffer.
Grade Stabilization Structure
Install a structure to control head cutting in channels as part of an approved
erosion control system.
Grassed Waterway
Construct a graded channel stabilized with suitable vegetation to convey runoff
from terraces, diversions, or other water concentrations or to control gully
erosion.
Hedgerow Planting
Establish dense vegetation in a linear design to screens and barriers to noise
and dust.
Lined Waterway or Outlet
Install a waterway or outlet with an erosion resistant lining of concrete,
stone, synthetic fabrics or other permanent material to provide for safe
conveyance of runoff from conservation structures or water concentrations or to
treat existing gully erosion.
Mulching
Apply plant residues or other suitable materials to the land surface to conserve
soil moisture, moderate soil temperature, provide erosion control, suppress weed
growth, establish vegetative cover, improve soil condition and increase soil
fertility, as part of an erosion control or organic farming system.
Nutrient Management (MGT)
Control the amount, source, placement, form and timing of nutrient applications
at either a basic or advanced level (two payment rates are offered). Basic
involves a nutrient budget and application record keeping system. Advanced
involves more frequent monitoring of the soil system. Both include the proper
use of manure or organic byproducts as a plant nutrient source, and improvement
in the physical, chemical and biological condition of soil.
Obstruction Removal
Remove and dispose of unwanted or hazardous structures, vegetation, and other
materials in order to facilitate the installation of new erosion control
measures.
Pest Management (MGT)
Use environmentally sensitive prevention, avoidance, monitoring and suppression
strategies to manage weeds, insects, and diseases at either a basic or advanced
level (two payment rates are offered). Basic involves crop scouting, economic
threshold evaluations and application record keeping. Advanced involves more
intensive use of tools or computer programs to reduce impacts further.
Residue Management, Mulch-Till (MGT)
Establish a new tillage system that manages the amount, orientation and
distribution of crop and other plant residues on the soil surface until just
prior to planting to reduce particulate air emissions and to reduce sheet and
rill erosion to the soil “T” level. Participants must document a minimum 30%
soil surface coverage at planting.
Residue Management, No-Till /Direct Seed (MGT)
Establish a new tillage system that manages the amount, orientation and
distribution of crop and other plant residues on the soil surface year-round,
while growing crops in narrow slots or residue-free strips in untilled soil, in
order to reduce particulate air emissions an reduce or control sheet and rill
erosion to the soil “T” level.
Riparian Herbaceous Cover
Establish grasses and forbs tolerant of intermittent flooding or saturated soils
in riparian areas to reduce sediment and other pollutants, to help stabilize
stream bank and shorelines, or to increase net carbon storage in the biomass and
soil.
Riparian Forest Buffer
Establish an area of trees and/or shrubs adjacent to water bodies to reduce
excess amounts of sediment, organic material, nutrients, and pesticides in
surface runoff and reduce excess nutrients and other chemicals in shallow ground
water flow.
Spoil Spreading
Properly dispose of surplus materials excavated to permit the installation of
approved erosion control practices.
Streambank and Shoreline Protection
Install structural or bio-engineered treatments used to stabilize banks of
streams or shorelines, reduce the offsite or downstream effects of sediment.
Strip Cropping
Establish new equal width strips of forages or small grains across a field with
an alternating pattern of row crops to reduce sheet and rill erosion and the
transport of sediment and other water-borne contaminants. Payment is limited to
the acres of narrow seeded crops on fields where soil loss is reduced to the
soil “T” value.
Structure for Water Control
Install a structure as part of an erosion control system to control the
direction or rate of water flow or maintain a desired water surface elevation.
Subsurface Drain
Install corrugated plastic tubing beneath the ground surface to control the
water table in fields where a documented phytophthera problem is preventing
implementation of a nutrient management system.
Terrace
Construct an earthen embankment (combination ridge and channel) across the field
slope to reduce soil erosion or retain runoff for moisture conservation.
Underground Outlet
Install a conduit beneath the surface of the ground to collect surface water
from terraces, diversions, surface drains or other approved practices and convey
it to a suitable outlet as part of an approved erosion control system.
Windbreak or Shelterbelt Establishment
Establish linear plantings of single or multiple row trees or shrubs to provide
living barriers to reduce airborne odors, particulates or chemical drift.
back to
beginning of Conservation Practices Eligible for Payment Assistance
Land must have been irrigated at least 2 of the past 5 years to be
eligible. In addition, all irrigation systems must have an efficiency
rating of at least 80%, and the contract must include Irrigation Water
Management as an agreed-to practice.
Air Resources Management
Install a solar system to power a new or existing irrigation pumping
plant;
or replace an existing 150 HP or smaller irrigation pump engine with a
new EPA Tier 3 or 4 certified engine.
Constructed Wetland
Construct a shallow water ecosystem to simulate natural wetlands in
order to reduce the pollution potential of runoff from agricultural
lands.
Critical Area Planting (tailwater system only)
In critical areas disturbed by the installation of a tailwater recovery
system, plant perennial vegetation such as trees, shrubs, grasses, or
legumes.
Grade Stabilization Structure (tailwater system only)
Install a structure to control head cutting in natural or artificial
channels installed as part of a tailwater recovery system.
Irrigation Water Conveyance
Install permanent underground high-pressure pipeline and appurtenances
as part of an approved irrigation system.
Irrigation System, Microirrigation
Install an irrigation system for uniform distribution of water directly
to the plant root zone by means of surface or subsurface applicators to
maintain soil moisture for optimum plant growth, effectively apply
agricultural chemicals, or reduce particulate matter emissions.
Irrigation System, Sprinkler
Install an irrigation system to uniformly and efficiently apply water by
means of nozzles operated under pressure, to maintain adequate soil
water for optimum plant growth, effectively apply agricultural
chemicals, or reduce particulate matter emissions.
Irrigation System, Tailwater Recovery
Install an irrigation system with facilities for the collection,
storage, and transportation of irrigation tailwater to conserve
irrigation water supplies and improve offsite water quality.
Irrigation Water Management (IWM) (MGT) Required for all contracts with
irrigation systems installed
Control the volume, frequency and application rate of irrigation water
in a planned, efficient manner to match the soil infiltration rate, soil
water holding capacity and crop need at various growth stages.
This practice requires the development of an IWM plan, soil moisture
monitoring, and water application record keeping. It includes the
installation of meters, monitors, and other appurtenances that aid in
the process of implementing an approved IWM plan.
Pumping Plant
Install a permanent pump at an existing water source to provide an
adequate water supply for irrigation. Payment is limited to pumps for
permanently installed irrigation systems, or pumps required to recycle
water through a tailwater recovery system.
Irrigation Regulating Reservoir (tailwater only)
Install a facility as part of a tailwater recovery system, when needed,
to collect and store excess runoff from an agricultural operation
Lined Waterway or Outlet (tailwater system only)
Install a waterway or outlet with an erosion resistant lining of
concrete, stone, synthetic turf reinforcement fabrics or other permanent
material to provide for safe conveyance of runoff from tailwater
recovery structures or water concentration areas.
Mulching (tailwater system only)
Apply plant residues or other suitable materials to the land surface to
provide erosion control on areas disturbed by construction of tailwater
facilities.
Obstruction Removal (tailwater system only)
Remove and dispose of unwanted or hazardous structures, vegetation,
landscape features, and other materials in order to facilitate the
installation of new tailwater recovery practices.
Pond Sealing or Lining (tailwater system only)
As part of a tailwater recovery basin, install a manufactured hydraulic
barrier consisting of a functionally continuous sheet of synthetic or
partially synthetic, flexible material to control seepage.
Precision Land Forming (tailwater system only)
Re-grade the surface of the land to allow the implementation of other
planned measures under an approved tailwater recovery system.
Roof Runoff Structure (tailwater system only)
Install structures to collect, control, and transport precipitation from
roofs as part of a tailwater recovery system.
Spoil Spreading (tailwater system only)
Properly dispose surplus materials excavated to permit the installation
of approved tailwater recovery practices.
Structure for Water Control (tailwater system only)
Install a structure as part of a tailwater recovery system that controls
the direction or rate of flow or maintains a desired water surface
elevation.
Underground Outlet (tailwater system only)
Install a conduit beneath the surface of the ground to collect surface
water from lined waterways or other approved tailwater recovery
practices and convey it to a suitable outlet.
back to
beginning of Conservation Practices Eligible for Payment Assistance
Payment is limited to practices designed to
address an existing resource concern for livestock that have been housed
or grazed on land under the operator’s control for at least 12 of the
previous 36 months. Consideration will be given for variations in animal
numbers normal for the operation. Waivers to this provision can be
requested in writing to the State Conservationist.
Air Resources Management (AC or MGT)
Use alternative fuels - E85 or bio-diesel (B20 or higher) - for on-farm
agricultural activities;
or install a solar energy-powered pump for the livestock watering
system.
Critical Area Planting
In critical areas disturbed by livestock or installation of erosion
control measures, plant perennial vegetation such as trees, shrubs,
grasses, or legumes.
Diversion
Construct a channel across the slope with a supporting ridge on the
lower side to interrupt water flow on slopes, reduce runoff damage, or
divert water away from active gullies or critically eroding areas.
Filter Strip
Establish a strip or area of herbaceous vegetation between grazing land
and environmentally sensitive areas to reduce sediment and particulate
organics in runoff, or serve as Zone 3 of a Riparian Forest Buffer.
Grade Stabilization Structure
Install a structure to control head cutting in channels as part of an
approved erosion control system.
Grassed Waterway
Construct a graded channel stabilized with suitable vegetation to convey
runoff from terraces, diversions, or other water concentrations or to
control gully erosion.
Riparian Herbaceous Cover
Establish grasses and forbs tolerant of intermittent flooding or
saturated soils in riparian areas to reduce sediment and other
pollutants, stabilize stream banks, and increase net carbon storage in
the soil.
Riparian Forest Buffer
Establish trees and/or shrubs adjacent to water bodies to reduce
pollutants in surface runoff.
Streambank and Shoreline Protection
Install structural or bio-engineered treatments to stabilize banks of
streams or reduce the offsite or downstream effects of sediment.
Structure for Water Control
Install a structure as part of an erosion control system to control the
direction or rate of water flow.
Underground Outlet
Install an underground conduit to collect surface water from diversions,
surface drains or other approved practices and convey it to a suitable
outlet.
Use Exclusion
Control livestock access to surface water areas through the use of
fencing, including gates where necessary.
THE FOLLOWING PRACTICES MUST BE PART OF AN APPROVED PRESCRIBED GRAZING
SYSTEM:
Animal Trails and Walkways
Establish travel ways to provide or improve access to forage or water or
to improve grazing efficiency and distribution.
Brush Management
Remove non-herbaceous plants to restore natural plant community balance,
manage noxious woody plants, or improve forage accessibility, quality
and quantity.
Fence
Install permanent fencing to divide an area of land to improve
distribution and timing of livestock grazing.
Heavy Use Area Protection
Stabilize areas around livestock watering facilities to reduce soil
erosion and improve air quality.
Pasture and Hayland Planting
Plant adapted forage species to improve livestock nutrition and/or
health or extend the length of the grazing season. Payment is for one
planting per pasture area during the life of the contract.
Pipeline
Install permanent underground pipe (inside diameter 8 inches or less) to
convey water from a supply source to points of use for livestock.
Prescribed Grazing (MGT)
Actively manage vegetation with grazing animals to improve the health
and vigor of forage, maintain a desired plant community, improve water
quality, reduce accelerated soil erosion, and improve soil condition.
Pumping Plant for Water
Install a pump to provide a dependable livestock water source.
Spring Development
Utilize available springs and seeps to provide water for livestock.
Stream Crossing
Construct a stabilized area across a stream to provide a travel way for
livestock in order to reduce sediment, nutrient, and organic loads in
the stream.
Watering Facility
Permanently install a watertight tank or trough to provide access to
water and facilitate proper grazing, or to protect streams, ponds and
water supplies from contamination.
Water Well
Install a new well, less than 6” in diameter, to replace an existing
water supply causing environmental damage.
back to
beginning of Conservation Practices Eligible for Payment Assistance
Payment is limited to practices designed to
address an existing resource concern for livestock that have been housed
or grazed on land under the operator’s control for at least 12 of the
previous 36 months. Consideration will be given for variations in animal
numbers normal for the operation. Waivers to this provision can be
requested in writing to the State Conservationist.
Note: a Comprehensive Nutrient Management Plan (CNMP) is required for
any contract that includes the storage of animal wastes produced on the
farm. NRCS will not provide assistance in the development of a CNMP
under the EQIP program.
The CNMP must be developed within the first 12
months of the contract by a certified Technical Service Provider hired
by the contract holder. All portions of the operation where waste is
generated or applied, whether under the EQIP contract or not, must be
included in the CNMP plan.
Comprehensive Nutrient Management Plan (CNMP)
Develop a written plan that details the handling of manure from the
point of production to the ultimate disposal site. Include all
conservation practices needed to implement the system and a time
schedule for implementation. Include a nutrient balance sheet based on
actual manure and soil test results when using manure as a soil
amendment. Structural conservation practices anticipated for the CNMP
may be included in the contract application and can be modified if
needed after contract approval. Payment is based on the number of animal
units that generate the waste and how the waste is utilized.
Air Resources Management (MGT)
Use alternative fuels - E85 or bio-diesel (B20 or higher) - for
on-farm agricultural activities.
Anaerobic Digester
Install a waste treatment impoundment to biologically treat waste and
capture biogas for energy, improve air quality, and reduce greenhouse
gas emissions.
Closure of Waste Impoundment
Close waste storage ponds no longer used for their intended purpose in
an environmentally safe manner as part of an overall waste management
system.
Composting Facility
Install a permanent facility to process raw manure into biologically
stable organic material to reduce the pollution potential to surface and
ground water.
Constructed Wetland
Construct a shallow water ecosystem designed to simulate natural
wetlands and reduce the pollution potential of wastewater from
agricultural lands.
Critical Area Planting
In critical areas disturbed by the installation of animal waste
facilities, plant perennial vegetation such as trees, shrubs, grasses,
or legumes.
Diversion
Construct a channel across the slope with a supporting ridge on the
lower side to divert water away from farmsteads or agricultural waste
systems, reduce runoff damages from upland runoff, or divert water away
from active gullies or critically eroding areas.
Heavy Use Area Protection
Stabilize areas with the least costly suitable material to reduce soil
erosion, or improve air and water quality. Payment is limited to areas
intensively used by animals during periods when pastures are not
available, based on the number of animals that the available pasture
normally supports during the growing season.
Payments for pavilion roofs are approved only when other runoff control
options are not feasible due to slope or soil limitations.
Manure Transfer
Install a system of structures or conduits to transfer animal manure
(including bedding, spilled feed, wash water, and other residues)
through a hopper or reception pit, conduit, and/or hauling equipment to
a manure storage/ treatment facility, loading area, or to agricultural
land for final utilization.
Obstruction Removal
Remove and dispose of structures, vegetation, landscape features, and
other materials necessary to install the waste management system.
Pumping Plant
Install a pump to transfer wastewater from source to storage areas
and/or from storage areas to disposal sites.
Roof Runoff Structure
Install structures that collect, control, and transport runoff from
roofs to prevent contamination by animal wastes, improve water quality
or reduce soil erosion.
Spoil Spreading
Dispose surplus materials excavated during installation of approved
animal waste management practices.
Solid/Liquid Separation Facility
Install a filtration or screening device, settling tank, or settling
basin to separate a portion of solids from the liquid waste stream in
order to better manage the associated nutrients.
Underground Outlet
Install an underground conduit to collect surface water from approved
practices and convey it to a suitable outlet.
Waste Facility Cover
Install a fabricated rigid, semi-rigid, or flexible membrane over a
waste storage facility to improve water or air quality or capture biogas
for energy production.
back to
beginning of Conservation Practices Eligible for Payment Assistance
Producers must have a valid NJ state aquaculture license and a
Shellfish Aquaculture Management Plan that
follows the NJDA/NJDEP Recommended Management Practices for Aquatic Farms. A map
indicating the gear layout, access points and buffer zones shall be provided to
NRCS by the applicant.
For 2008, the following practices are included. Additional practices may be
added in future years.
Air Resources Management
Use alternative fuels (MGT) - E85 or bio-diesel (B20 or higher) - for on-farm
agricultural activities.
Filter Strip
Establish a strip or area of herbaceous vegetation between the effluent outlet
or production water discharge point and any environmentally sensitive areas to
reduce sediment and particulate organics in runoff. The strip must meet the
requirements of the NJ DEP AMP for filter strips in addition to NRCS standards,
including any minimum widths or distances from other land uses.
Shellfish Aquaculture Management
Improve water quality by following either a basic or advanced system of
practices designed to reduce or control toxic emissions directly into the water.
Syst4ems include use of low-copper paints, upgrading to low-emission equipment
and protection from leaks and spills.
Stream and Shoreline Protection
Stabilize and protect the banks of shorelines estuaries with vegetation or
hardscape to prevent the loss of land, or damage to land uses or facilities
adjacent to the banks. Required permits are the responsibility of the applicant.
back to
beginning of Conservation Practices Eligible for Payment Assistance
Practices must meet the requirements of the NJ Stormwater Management Rules and treat impervious surfaces that were in
existence on its effective date of (February 2, 2004).
Constructed Wetland
Construct a shallow water ecosystem designed to simulate natural
wetlands to reduce the pollution potential of runoff from agricultural
lands.
Critical Area Planting
In critical areas disturbed by the installation of runoff management
practices, plant perennial vegetation such as trees, shrubs, grasses, or
legumes.
Diversion
Construct a channel across the slope with a supporting ridge on the
lower side to interrupt water flow on slopes, reduce runoff damage, or
divert water away from active gullies or critically eroding areas.
Grade Stabilization Structure
Install a structure to control head cutting in natural or artificial
channels as part of an approved storm water management system.
Lined Waterway or Outlet
Install a waterway or outlet with an erosion resistant lining of
concrete, stone, synthetic turf reinforcement fabrics or other permanent
material to provide for safe conveyance of runoff from storm water
management structures or water concentration areas.
Mulching
Apply plant residues or other suitable materials to the land surface to
provide erosion control, suppress weed growth, or establish vegetative
cover.
Obstruction Removal
Remove and dispose of unwanted or hazardous buildings, structures,
vegetation, landscape features, and other materials in order to
facilitate the installation of new storm water management practices.
Pond Sealing or Lining
Install a manufactured hydraulic barrier consisting of a functionally
continuous sheet of synthetic or partially synthetic, flexible material
as part of a water and sediment control basin to control seepage.
Precision Land Forming
Re-grade the surface of the land to allow the implementation of other
planned measures under an approved storm water runoff management system.
Riparian Herbaceous Cover
Establish grasses and forbs tolerant of intermittent flooding or
saturated soils in riparian areas to reduce the amount of sediment and
other pollutants or to help stabilize stream bank and shorelines.
Riparian Forest Buffer
Establish an area of trees and/or shrubs adjacent to water bodies to
reduce excess amounts of sediment, organic material, nutrients, and
pesticides in surface runoff and reduce excess nutrients and other
chemicals in shallow ground water flow.
Roof Runoff Structure
Structures that collect, control, and transport precipitation from
roofs, installed to reduce soil erosion, increase infiltration, or
increase water quantity.
Runoff Management System
Install site-specific components of a runoff management system to meet
NJ storm water management regulations.
Spoil Spreading
Dispose of surplus materials excavated to permit the installation of
approved storm water runoff management practices.
Structure for Water Control
Install a structure, required as part of a tailwater recovery or storm
water management system, which conveys water, controls the direction or
rate of flow, or maintains a desired water surface elevation.
Underground Outlet
Install a conduit beneath the surface of the ground to collect surface
water from surface drains, lined waterways, or other approved practices
and convey it to a suitable outlet.
Water and Sediment Control Basin
Install a basin, as part of a Storm Water Runoff Management System, to
collect and store excess runoff water from an agricultural operation.
back to beginning of Conservation Practices Eligible for Payment
Assistance
Contact:
Janice Reid, Assistant State Conservationist for Programs,
(732) 537-6042
< Back to Environmental Quality
Incentives Program
Last Modified:
May 27, 2008
|